CURRENT PROJECTS

The Regency at 5th Avenue Condominiums | Pittsburgh, PA

Burchick Construction has been retained as the General Contractor to perform substantial mechanical and electrical system upgrades for this facility. The scope of work included a significant electrical system and equipment upgrade and replacement of the individual HVAC units in each of the 19 condominiums throughout the facility. Burchick began work in mid-2023 with selective demolition, and preliminary work associated with the HVAC upgrades. HVAC units were installed in 3 rd and 4 th quarter 2023. The equipment for the electrical systems upgrades was delivered in

January 2024 and these systems are scheduled to be installed and energized by the end of February 2024. This project required close coordination with all tenants of the facility to ensure electrical and mechanical services were always available during occupancy.